Florida General Contractor Project Management Exam: free practice test

The second Division I trade part. It focuses on scheduling, job-site safety under OSHA 29 CFR 1926, cost control and managing the work in the field.

Or open the free Florida Project Mgmt study dashboard: flashcards, notes and your Readiness Score, no signup →

About the Florida Project Mgmt exam

The second Division I trade part. It focuses on scheduling, job-site safety under OSHA 29 CFR 1926, cost control and managing the work in the field.

What's on the exam

Florida Project Mgmt
Scheduling and CPM
7 key facts
Fall Protection and Access
7 key facts
Excavations and Trenching
7 key facts
Scaffolds, Fire and Reporting
7 key facts
Cost Control and Earned Value
6 key facts
Cranes and Rigging
7 key facts
Quality Control and Close-out
7 key facts

Each branch is a topic in the official outline. Members see every key fact on the full mind map. Read the free study guide →

How to pass the Florida Project Mgmt exam

  • OSHA lookup speed wins this exam. Tab subparts M (fall protection), L (scaffolds), P (excavations) and CC (cranes).
  • Know total float vs. free float, and how to find the critical path by hand.
  • Most cost questions are simple ratios: CPI = EV ÷ AC, SPI = EV ÷ PV.

Save your results and get your Readiness Score

Create a free account after the test: your score by topic, a mistakes bank, the first study-notes topic, flashcards and the Construction Math Formula Sheet.

Take the test first

What's in the full Florida Project Mgmt prep

Full question bank

600+ exam-style questions written to each official outline. Every answer explained, with the rule it comes from.

Timed exam simulator

Real question counts and time limits, so test day feels like practice day.

Exam Readiness Score

One 0 to 100 number that tells you when you're ready to book. Reach 80 and you're covered by our Pass Guarantee.

Flashcards + spaced repetition

530+ cards that come back right before you'd forget them. Five minutes a day keeps every number fresh.

Key study notes

Each topic boiled down to the 5 to 7 facts that get tested, with the statute or code section.

Mind maps

See the whole exam on one screen: every topic and the facts under it.

Sample questions with answers

These are the questions in the free test above, with answers. Try the test first. You'll learn more by getting some wrong.

1. Total float is the amount of time an activity can be delayed without delaying:
Answer: The project completion date. Total float protects the finish date. Free float is the delay possible without delaying the early start of any successor.
2. Earned value is $90,000 and actual cost is $100,000. The cost performance index (CPI) is:
Answer: 0.90 (over budget). CPI = EV ÷ AC = 90,000 ÷ 100,000 = 0.90. Below 1.0 means you're spending more than the value of work earned.
3. Earned value is $45,000 and planned value is $50,000. The schedule performance index (SPI) is:
Answer: 0.90. SPI = EV ÷ PV = 45,000 ÷ 50,000 = 0.90, which means the job is behind schedule.
4. When operating a crane near power lines up to 50 kV, the minimum clearance that must be maintained is:
Answer: 10 feet. 29 CFR 1926.1408 Table A: 10 feet for lines up to 50 kV. Greater voltages require more clearance.
5. Daily inspections of excavations and protective systems must be made by a:
Answer: Competent person. 29 CFR 1926.651(k)(1): a competent person inspects before work starts and as needed through the shift.
6. A stairway, ladder, ramp or other safe means of egress is required in trenches 4 feet or deeper so that workers travel no more than how far laterally to reach it?
Answer: 25 feet. 29 CFR 1926.651(c)(2): no more than 25 feet of lateral travel.
7. A stairway or ladder must be provided at all points of access where there is a break in elevation of:
Answer: 19 inches or more. 29 CFR 1926.1051(a): 19 inches or more, unless a ramp, runway, embankment or personnel hoist is provided.
8. On a construction site, a fire extinguisher rated at least 2A must be provided for each 3,000 sq ft and placed so travel distance to it is no more than:
Answer: 100 feet. 29 CFR 1926.150(c)(1)(i): travel distance to the nearest extinguisher must not exceed 100 feet.
9. Fall protection is required for employees on a scaffold more than how high above a lower level?
Answer: 10 feet. 29 CFR 1926.451(g)(1): 10 feet for scaffolds (the general construction trigger is 6 feet).
10. Scaffold planks must extend over their end supports by at least:
Answer: 6 inches. 29 CFR 1926.451(b)(4): at least 6 inches, and no more than 12 inches unless cleated, restrained or guarded.
11. Activity A takes 5 days and activity B takes 3 days. B can start 2 days after A starts (start-to-start with a 2-day lag). If A starts on day 0, the earliest B can finish is:
Answer: Day 5. B starts on day 2 (0 + 2 lag) and lasts 3 days, so it finishes on day 5.
12. A bar chart showing activities against a time scale, without logic ties, is a:
Answer: Gantt chart. A Gantt (bar) chart shows durations on a calendar but doesn't show dependencies. CPM/precedence diagrams show logic.
13. Ground-fault circuit interrupters on construction sites are required to protect workers from:
Answer: Electrical shock from ground faults. 29 CFR 1926.404(b)(1): GFCIs (or an assured equipment grounding program) protect workers on 120-volt, 15/20/30-amp receptacle outlets.
14. Under OSHA's construction standards, who is responsible for providing required personal protective equipment at no cost to employees in most cases?
Answer: The employer. 29 CFR 1926.95: the employer pays for required PPE, with narrow exceptions such as ordinary safety-toe footwear and prescription safety eyewear.
15. A list of items to be completed or corrected before final completion is called the:
Answer: Punch list. The punch list is prepared around substantial completion and must be finished before final payment.

Get the full Florida Project Mgmt prep

Single Exam

$97 one-time
6 months of access · no subscription
  • Full Florida Project Mgmt bank (50 questions)
  • Timed exam simulations
  • Study notes, flashcards & mind maps
  • Spaced repetition + mistakes bank
  • Readiness Score & detailed reports
  • Video lessons as they release
  • 5 bonuses: formula sheet, tabbing guide, study planner and more
  • Pass Guarantee: complete the prep, pass or 100% back
Best value · save 75%

All-Access Yearly

$147/year
Every exam · works out at $12.25 a month · cancel anytime
  • All 12 exams, including state Business & Law
  • Full question banks + timed simulations
  • Study notes, flashcards & mind maps
  • Spaced repetition + mistakes bank
  • Readiness Score & detailed reports
  • Video lessons as they release
  • New exams added during your access
  • 5 bonuses: formula sheet, tabbing guide, study planner and more
  • Pass Guarantee: complete the prep, pass or 100% back

All-Access Monthly

$49/month
Every exam · cancel anytime
  • All 12 exams, including state Business & Law
  • Full question banks + timed simulations
  • Study notes, flashcards & mind maps
  • Spaced repetition + mistakes bank
  • Readiness Score & detailed reports
  • Video lessons as they release
  • New exams added during your access
  • 5 bonuses: formula sheet, tabbing guide, study planner and more
  • Pass Guarantee: complete the prep, pass or 100% back

All-Access renews automatically until you cancel. Cancel any time from your account; you keep access until the end of the period you've paid for.

Just need one tool?

Unlock a single module for Florida Project Mgmt: 6 months, one-time payment. All three separately cost $127; Single Exam gets you all of them for $97.

Question Bank$49

Every practice question for one exam, with explanations, your mistakes bank and reports.

  • Every question (50), every answer explained
  • Mistakes bank + detailed reports
Exam Simulator$39

Full-length timed simulations with real question counts and time limits.

  • Full-length timed simulations
  • Real question counts and time limits
Study Pack$39

Every study-notes topic, every flashcard with spaced repetition, and the full mind map.

  • Every study-notes topic
  • All flashcards + spaced repetition
  • The full interactive mind map
Pass Guarantee on Single Exam and All-Access. Complete the full prep, sit your exam within 60 days, and if you don't pass we refund 100%. See the requirements
Secure checkout by Stripe Card, Apple Pay, Google Pay Pass Guarantee

Licensing guide

How to Get a Contractor License in Florida (2026): To get a statewide Florida contractor license, you prove 4 years of experience (or a mix of college and experience), pass the state exams, and apply to the Construction Industry Licensing Board (CILB) through DBPR with a credit report, insurance, workers' comp and fingerprints. General, building and residential contractors (Division I) must pass three open-book exams: Business and Finance, Contract Administration and Project Management. Expect the full process to take a few months once your experience is in place.